Drummond Road Drainage Upgrade Works
The necessary upgrade of drainage infrastructure at Drummond Road, Shepparton was identified through Council's 2020 Drainage Strategy, which focused on identifying and addressing historic and nuisance stormwater issues that affect the community.
This strategy assisted with creating a plan to prevent future flooding issues at the key intersection of New Dookie Road and Drummond Road.
The Drummond Road drainage upgrade involved installing new drainage pipes, stormwater pits, concrete kerbing, and resurfacing sections of the road.
The contract for these works was awarded at the Ordinary Council Meeting in August 2024 to Mawson Constructions Pty Ltd.
Timeline of works
- Completed works - December 2024
Construction of the new drainage system in Drummond Road from Joseph Baldwin Place is complete, with asphalting of the works undertaken to date.
- Completed works - January 2025
The installation of pits and pipes along Drummond Road is completed and that Drummond Road is temporarily reopened with speed restrictions in place.
- Completed works - February 2025
The installation of pits and pipes along New Dookie Road within the traffic island and the left hand turn lane into Drummond Road from New Dookie Road is completed.
- Water main replacement works
Tuesday 22 April to Tuesday 13 May 2025East and West sides of Drummond Road, at the intersection of New Dookie and Drummond Roads.
Note: intersection will remain open with speed restrictions in place.
- Construction of connecting stormwater pits and pipes
Wednesday 14 May to Thursday 22 May 2025East side of Drummond Road at the intersection of New Dookie and Drummond Roads.
Note: intersection will remain open with speed restrictions in place.
- Asphalt Surface Works
Friday 23 May to Tuesday 27 May 2025New Dookie and Drummond Roads intersection.
Note: intersection will be closed. During this time access and egress to Drummond Road businesses will be via Old Dookie Road ONLY.
Access to businesses within the vicinity of the works will be maintained throughout the construction period.
Have a question or concern?
For further information please contact Council’s Project Manager for any queries via phone (03) 5832 9700 or mail projects@shepparton.vic.gov.au
These works are fully funded by the Australian Government’s Roads to Recovery (RTR) Program.