Works at GV Link Enterprise Park, at 250 Toolamba Road, Mooroopna, continue to progress, with Stage 1 of the roundabout works nearing completion and the subdivided lots taking shape.
Works at the site commenced in April, with Greater Shepparton City Council and contractor BMD Urban, making good progress on Stage 1. This stage involves:
Bulk earthworks across the four lots are nearing completion. Works along Simson Road and Innovation Drive – a new road through the subdivision – are well underway, along with construction of the site’s wetland.
Stage 1 of the roundabout is now structurally complete, with asphalt works planned for January 2026. Stage 2, which involves works alongside the railway line, is scheduled to commence in late January, which will result in a change of traffic conditions to enable the Stage 2 works to be completed.
Utility service connections have also progressed well, with works through the Mooroopna township now complete. Connections towards Rumbalara Road are expected to be finished before Christmas, while works further along Toolamba Road, towards the Mooroopna Police Station and across the Midland Highway, will continue in early 2026.
Mayor, Councillor Shane Sali, thanked the community for their patience and understanding while works have been undertaken.
“We understand the significant impact these works have had on traffic flow in the area. We appreciate the community’s patience while construction has been underway and traffic diversions have been in place,” he said.
“The team have made great progress on site this year. GV Link Enterprise Park will support greater investment in our region, paving the way for future development stages, new industry and key projects.
“It’s fantastic to see strong partnerships with local businesses and community groups maintained throughout the works, ensuring shared benefits and economic growth for Greater Shepparton.”
Several local community groups have already benefited from the project, receiving a share of the timber recovered from the bulk earthworks. The Dookie United Football Netball Club and Mooroopna Men’s Shed have received felled large timber for their community fundraising initiatives, while the Goulburn Broken Catchment Management Authority has also received large root balls to support native fish habitat recovery.
BMD Urban Regional Operations Manager, Greg Stevens, said significant local supplier investment was a hallmark of the project.
“We have approximately 30 local - small to medium - enterprises involved in the construction, which was a commitment from BMD Urban that is being delivered. We are proud to be supporting local suppliers to deliver a project that creates jobs and opportunities for Greater Shepparton,” he said.
Works on site will pause over Christmas, with after-care traffic management remaining in place. Construction will recommence in January, with Stage 1 of GV Link Enterprise Park expected to be completed by the end of April 2026.
To find out more about GV Link Enterprise Park, for recent photos of the works or to subscribe for project updates, visit the Major Projects Page.
More News from Greater Shepparton
Thursday 12th of March,
Upcoming Community Satisfaction Surveys in Greater Shepparton
Council is encouraging residents to share their thoughts on Council and its services through the third quarter Local Government Community Satisfaction Survey. Read more
Tuesday 10th of March,
Road patching works across Shepparton and Mooroopna
Council wishes to advise that road patching works are programmed for several streets and roads throughout Shepparton and Mooroopna on Saturday 14 March 2026. Read more
Tuesday 10th of March,
RiverConnect and Greater Shepparton Lighthouse Project partnership blossoms to deliver education program
RiverConnect and Greater Shepparton Lighthouse Project (Lighthouse) are pleased to announce the introduction of Bees and Blossoms Pollinator Education Sessions. Read more
Tuesday 10th of March,
Traffic management changes - Toolamba and Simson Road intersection
Council wishes to advise that traffic management at the intersection of Toolamba Road and Simson Road, Mooroopna will change from Tuesday 17 March 2026. Read more
Tuesday 10th of March,
Speed reductions to be introduced on several roads in Shepparton South East
Council wishes to advise residents of upcoming speed limit changes on several roads in Shepparton’s South East, aimed at improving safety and supporting the area’s ongoing development. Read more
Friday 6th of March,
KidsTown closure extended due to weather delays
Council is advising the community that the current closure of KidsTown Adventure Playground will be extended until Friday 20 March 2026. Read more
See All News
Want to get the latest news and events in your Facebook feed?
Just go to our Facebook page and click the Like button.
More Events in Greater Shepparton
Friday 13th of March,
Puff Walk
Walk. Talk. Laugh. Repeat! Read more
Friday 13th of March,
Testadura Productions presents The Italian Divorce
You can leave your wife but you can never leave your family. After sellout seasons in Melbourne, Sydney and Adelaide, the hit show is back! It’s loud, heartfelt, and hysterically relatable…it’s like watching… View on Riverlinks
Friday 20th of March,
Puff Walk
Let’s walk and talk. Read more
Friday 20th of March,
Jeff Carter presents Thank you for the Music -- The Ultimate ABBA Performance
Get ready to say, “Thank you for the Music” the Ultimate ABBA performance. View on Riverlinks
Saturday 14th of March,
Shepparton Italian Festa
The Shepparton Italian Festa is set to bring vibrant culture, food, and community spirit! Read more
Sunday 15th of March,
Sit Spots
Slow down and connect Read more
See All Events