Drummond Road Drainage Upgrade Works

The necessary upgrade of drainage infrastructure at Drummond Road, Shepparton was identified through Council's 2020 Drainage Strategy, which focused on identifying and addressing historic and nuisance stormwater issues that affect the community.

This strategy assisted with creating a plan to prevent future flooding issues at the key intersection of New Dookie Road and Drummond Road.

The Drummond Road drainage upgrade involved installing new drainage pipes, stormwater pits, concrete kerbing, and resurfacing sections of the road.

The contract for these works was awarded at the Ordinary Council Meeting in August 2024 to Mawson Constructions Pty Ltd.

Timeline of works

  • COMPLETED — December 2024

    Construction of the new drainage system in Drummond Road from Joseph Baldwin Place is complete, with asphalting of the works undertaken to date.

  • COMPLETED — January 2025

    The installation of pits and pipes along Drummond Road is completed and that Drummond Road is temporarily reopened with speed  restrictions in place.

  • COMPLETED — February 2025

    The installation of pits and pipes along New Dookie Road within the traffic island and the left hand turn lane into Drummond Road from New Dookie Road is completed.

  • COMPLETED — 22 April to 13 May 2025

    Water main replacement: East and West sides of Drummond Road, at the intersection of New Dookie and Drummond Roads. 

  • COMPLETED — 14 to 22 May 2025

    Connecting stormwater pits and pipes: East side of Drummond Road at the intersection of New Dookie and Drummond Roads.

  • COMPLETED — 23 to 27 May 2025

    Asphalt surface: New Dookie and Drummond Roads intersection.

Have a question or concern?

For further information please contact Council’s Project Manager for any queries via phone (03) 5832 9700 or mail projects@shepparton.vic.gov.au 

These works are fully funded by the Australian Government’s Roads to Recovery (RTR) Program.