Lenne Street Drainage Upgrade Works

Greater Shepparton City Council is pleased to officially acknowledge the completion of the Lenne Street Drainage Upgrade, marking a significant milestone in improving stormwater management for the Mooroopna community.

The Lenne Street, Mooroopna area was identified for urgent improvements, with a focus on addressing stormwater issues that have affected the community and creating a plan to increase efficiency of stormwater management.

Council identified improvement opportunities for the existing stormwater drainage network to mitigate the rain event issues in the area during sudden heavy downpours.

The project was split into stage 1 and 2 for the delivery with both stages now marked as complete. Read our media release. 

Project overview

The project included the following:

  • STAGE 1: April to November 2025Read description of completed Stage 1 works
  • STAGE 2: May to August 2026Read description of completed Stage 2 works

20 August 2026 - Works complete

15 May 2026 - Pump station delivery and installation

Photos of pump station delivery and installation.

16 April 2026 - Stage 2 works underway

13 May 2025 - Stage 1 works commenced

Contact us

For further information please contact Council's Project Delivery Team on 5832 9700 or by emailing projects@shepparton.vic.gov.au.

These works were 50 percent funded by the Disaster Ready Fund. 
More information can be found on the NEMA website